Updated June 14: Clements Bridge Rd. Closure / Construction info

Updated June 14: Clements Bridge Rd. Closure / Construction info

Update on June 14, 2016:

BARRINGTON – 1-2 WEEKS
STARTING TODAY ( 1 WEEK) – BETWEEN GLOUCESTER PIKE AND E. ATLANTIC – TC = Alternating Traffic

* Concrete Curb and Handicap Ramp installation
BETWEEN GLOUC. PIKE AND WILLIAMS (1 WEEK) – TC = DETOUR

* Crew will continue concrete curb work towards and including in front of RITE AID (Gloucester Pike) and at Shreve

RUNNEMEDE – 1 WEEK
TODAY BETWEEN NJSH 168 (BLACK HORSE PIKE AND IRISH HILL ROAD – TC = CONTINUED DETOUR

* Storm Sewer Crossings

*************

Update on June 13, 2016:

Clements Bridge Road Update

PSE&G will be replacing the gas main on June 15 and 16 between Williams and Gloucester Pike. This will be a road closure so the detour will be in place.

 

***********

Update on June 7, 2016:

  • Week of June 7-11, 2016 detours will be between Gloucester Pike and Williams. (related to NJA Water project)
  • Detour between Gloucester Pike and E. Atlantic will be starting up again the week of June 20th (related to NJA Water project) for concrete roadway restoration.

*********************

Update on May 18, 2016

South State, Inc. General Contractors will be doing the following work in and around Clements Bridge Road:
5/18/16 – 6/3/16 – Install all drainage work in Runnemede Section
5/18/16 – 6/3/16 – Complete all tie ins to water main.
6/6/16 – 6/24/16 – Complete concrete restoration in Barrington portion of water main.
6/6/16 – 6/24/16 – Complete all concrete curb, sidewalk, handicapped ramps, etc. on Clements Bridge Road

Runnemede work will be a 1 way detour as they’ve previously been doing.
The Barrington work will require full detours like they’ve done in the past.

So they will be jumping back and forth between the 2 different Barrington detours.

*********************

Update on April 18, 2016:
South State, Inc. General Contractors will be closing the following roads:

Monday 4/18 & Tuesday 4/19 – Gloucester Pike to Williams Avenue for Water Main work
Wednesday 4/20 – Friday 4/29 – E. Atlantic to Gloucester Pike for Water Main services/tie ins

PLEASE NOTE THAT ALL BARRINGTON BUSINESSES ARE STILL OPEN FOR BUSINESS DURING CONSTRUCTION. WE APPRECIATE YOUR CONTINUED PATIENCE AS THE REPAIRS ARE COMPLETED.

*********************

IMPORTANT—starting Wednesday, March 23, traffic will be detoured while NJAWC replaces the water main. We originally thought alternating lanes of traffic would be open but that has changed and traffic will be detoured. Traffic coming from Runnemede will be detoured down Gloucester Pike and traffic coming from Haddonfield will be detoured down Atlantic Avenue. The detour plan will alternate as the project moves along. The first phase of detour will be from Haines Avenue to Gloucester Pike and according to the schedule we got from the County will continue until April 10. As we get more information we will provide updates. Camden County will be doing a reconstruction of Clements Bridge Road starting March 28. The project will run from Haines Avenue and go all the way into Runnemede. Although the County project will begin March 28, New Jersey American Water will be doing some preparation work starting March 21. While the County has the roadway open, NJAWC will be replacing some water mains. The project is expected to be complete by July 28. There will absolutely be traffic difficulties during construction. Clements Bridge Road will be detoured starting March 23 and will continue to be detoured through June 6. Please expect significant delays and be patient or find an alternate route for your daily travels. This project is sorely needed as Clements Bridge has been in disrepair for quite some time. For more information you can contact Camden County, Anthony O’Toole, at 856-566-2974 or 2980. To contact NJAWC regarding their work, call Edward Opczynski III at 856-764-6924. LAST UPDATED March 22, 2016

DETOUR INFORMATION HERE: Clements Bridge Road will be detoured in two (2) Phases (Click here for Plan 1 & Plan 2 maps).  The first is between Gloucester Pike and E. Atlantic and that is shown on attached schedule as (Haines to Gloucester Pike). The second is between Gloucester Pike and Williams and shown on above maps as (Gloucester Pike to Williams). Please note as per this schedule the Detour goes from one phase to the next as per the start and stop dates. Clements Bridge Road will be open on weekends and at the end of construction day (hopefully between 3:30 – 5:30PM). All vehicular traffic must have access to the businesses and schools. All buses, emergency vehicles and authorized vehicles will be allowed through the closure area at all times.